Regarding the contract for composition work and the seasoning and salting of planks
Document 1796Contract for composition work has already been made; could have been done more cheaply at Philadelphia. Discusses the seasoning and salting of the frigate planks. Postpone journey to Norfolk until further instructions given.
100%
⇣No human transcription currently available for this document.
This transcription was generated by machine using Anthropic's Claude Code (a mix of sonnet and opus models). It may contain errors or inaccuracies. Please verify against the document image. Learn more about our generative AI methodology.
Sir, You will be pleased forthwith to proceed to
Newjort Portsmouth in New Hampshire and Boston
The general Objects of your Journey to these Towns
1° To examine and assort and arrange into distinct parcels the Shiptimbers and planks the property of the U.S. in the different Yards in Newjort Portsmouth and Boston
2° To ascertain into the State of the Naval Stores at those places and procure for them greater protection and security where assisted —
(3 To obtain from the principal Shipbuilders of Newjort Portsmouth and Boston upon what terms, and within what time they will engage to build a 36 gun Frigate of the Dimensions ascribed in sketch A.
You will arrange the Shiptimbers and Planks according to the following Classes
Class N° 1 will comprehend the number of pieces of live Oak at the respective spaces fit for the Frigates whose building have been suspended and exclusive of the pieces requisite for those under Construction.
In this Class as well as in all the other Classes you will assort the timbers or planks agreeably to their thickness and uses and &c [undecipherable] Bullock September hewed [undecipherable] the exact number of each.
Class N° 2 will comprehend the number of pieces of live Oak suitable for the Frigates [building as?] suspended but which may be used in the Construction of the Frigate sketch A.
Class N° 3 will comprehend the number of pieces of live Oak unsuitable for any of the Frigates including sketch A by reason of defects or other Causes noting those Causes
Class N° 4 will exhibit & the number of pieces of white Oak suitable and wanted for Frigate Sketch A & the number of pieces unsuitable and not wanted for the Frigates under Construction or for Frigate Sketch A.
Class N° 5 will exhibit a Statement of the Plank in each yard arranged according to their Thickness, lengths and kinds [undecipherable] wanted for Frigate Sketch A & exclusive of [undecipherable] the Frigate at Boston & the Surpluss divided into its Series —
Class N° 6 will exhibit the Number, [and] kinds of Masts and Spars. (
It being contemplated to dispose of the timbers assorted under Class N° 3 those under Class N° 4 and the plank under [Class N° 3] and such of the Masts and Spars as may not be wanted, or would [injure] by keeping you will therefore endeavour to form an Opinion of what they would probably sell for, at the places where deposited and report the same.
The timbers wanted from Newjort for the Frigates building at Philad. and Baltimore are to be exclusive from your estimates.
You are to see the timbers destined for future use carefully piled up as well as the timbers assorted for Frigate Sketch A and the whole protected against the weather by proper sheets, and against Theft by [enclosures].
In piling it care must be taken so to dispose of that suitable for Frigate Sketch A that it may be removed at any time without disturbing the other.
It will also be proper also that you should visit the warehouses where Naval Materials are Stored examine the State in which they are, and whether they are well secured, and take [an exact] inventory of the different kinds and quantity of each kind.
In ascertaining the terms on which the Shipbuilders at the Towns you are to visit will contract to build a 36 gun Frigate conformably to sketch A you will require
1. Their terms for such a Frigate they providing the timber and other Materials
2. Their terms the U.S. providing the timber and plank
3. Their terms they taking the timber and plank fit for the purpose at valuation
4. That their proposals be in writing, and the time they will finish her in expressed —
But to obviate delay as much as possible, you will on your arrival at Newjort obtain from one or more of the principal Shipbuilders upon what terms, and in what time they will engage to complete a Ship of the Dimensions of sketch A and forward the same to the Secretary of War, you will also write to Portsmouth and Boston to the same purpose stating the size and dimensions and requesting them to forward to the Secretary of War their terms, and the time they will engage to deliver such a [undecipherable] of well seasoned timber. Their terms the U.S. providing the timber, or they taking it at valuation may be obtained afterwards —
It is necessary that there should be responsible persons appointed to take charge of the timber and Naval Materials; you will therefore enquire for such, report their names and what they would consider as reasonable compensation.
you will also examine into, and report the progress made in the Frigate building at Boston and the probable time when she may be launched.
I have directed a Warrant to be made out in your favour for Three Hundred Dollars to cover the expences attending your Mission. It will be proper that you should take vouchers or receipts for your disbursements to enable you to settle for this advance with the Accountant of the War Department — Given at the War Office this 12. Day of July 1796 —
J. M. M.
Secy of War
Type
Letterbook
Description
Contract for composition work has already been made; could have been done more cheaply at Philadelphia. Discusses the seasoning and salting of the frigate planks. Postpone journey to Norfolk until further instructions given.
Date
07/07/1796
Recipient
Sent from
Philadelphia
Document number
1796070715055
Page start
176
Notable persons
Captain Thomas Truxton
Joshua Humphreys
naval constructor
superintendent
Truxtun
James McHenry
Secretary of War
War Department
War Office